software_dev #26466

closed

software_dev #26445: Internal Tools

BCU EOL GUI

software_dev #26466: BCU EOL GUI

Added by Prakash Vastrakar 11 days ago. Updated about 18 hours ago.

Status:
Closed
Priority:
P2 - Critical
Assignee:
Target version:
-
Start date:
10 Aug 2026
Due date:
18 Aug 2026
% Done:

100%

Estimated time:
(Total: 0:00 h)

Subtasks 1 (0 open1 closed)

software_dev #26467: BCU-1.5 EOL Testing GUIClosedomkar.dipak -10 Aug 202618 Aug 2026

Actions

Updated by Prakash Vastrakar 11 days ago Actions #1

  • Due date set to 18 Aug 2026
  • Assignee set to omkar.dipak -
  • Priority changed from P4 - Minor to P2 - Critical
  • Start date set to 11 Aug 2026

Updated by Prakash Vastrakar 11 days ago Actions #2

  • Subtask #26467 added

Updated by Prakash Vastrakar 11 days ago Actions #3

  • Tracker changed from Software_TOOLS to software_dev

Updated by Prakash Vastrakar 11 days ago Actions #4

  • Status changed from New to In Progress
  • % Done changed from 0 to 50

Updated by Prakash Vastrakar about 18 hours ago Actions #5

  • Status changed from In Progress to Closed
  • % Done changed from 50 to 100